Within the framework of 2026 Public Investment Budget, The Mayor of Nkum Council, the Contracting Authority, on behalf of the Republic of Cameroon, hereby launches an open invitation to tender, for the rehabilitation of the WAWA Bridge along the NSEH – MEMFU road stretch in Nkum Municipality; Bui Division, Northwest Region. It is not subject to any allotment.
|
Name of project |
Amount of project |
Amount of bid bond |
Cost of tender file |
|
Rehabilitation of the WAWA Bridge along the NSEH – MEMFU road stretch in Nkum Municipality |
50,000,000 CFA F |
250 000 CFA F |
70,000 CFA F |
Works to be realized on the account of this project prominently consist on building a bridge of five meters span and three by three meters of mouth size in order to definitely re-establish the traffic on the interrupted road.
Therefore, the main actions to undertake in order to ensure the sustainability of the project are:
- The installation of the base camp and technical platform;
- The cleaning of the working area;
- The demolition of the existing structure;
- The putting in place of deviations if possible;
- The rubble cut of shoulders and river banks;
- The excavation of foundations in riverbed or in plain land;
- The putting in place of an underpinning for the basement;
- The laying down of footings in reinforced concrete measured at 400 kg/m3;
- The raising up of embedded posts in reinforced concrete measured at 400 kg/m3;
- The raising up of abutments in masonry stones including wings;
- The putting in place of gargoyles in abutments and the deck;
- The construction of tie beams in reinforced concrete measured at 400 kg/m3;
- The construction of girders and struts in reinforced concrete measured at 400 kg/m3;
- The supply and putting in place of bridge girders and struts in IPE 50 will be optional;
- The construction of the bridge’s deck in reinforced concrete measured at 400 kg/m3;
- The construction of wheel guides in reinforced concrete measured at 400 kg/m3;
- The putting in place of mix reinforced concrete posts and metallic tubes guardrails;
- The putting in place of sidewalks on the bridge;
- The construction of masonry stone protective flooring on the slopes behind the heads;
- The backfilling behind the structure and adjacent to the work;
- The grading of the roadway to ease the traffic;
- The supply putting in place of the bridge bridge’s sign panels;
- The planting of nursed water friendly trees (raffia vinifera) at the river banks;
- All the necessary arrangement for the proper functioning of the site;
- Any other task needed for the smooth completion of works.
The framework of each unit in reinforced concrete measured at 400 kg/m3 (posts, tie beams, girders, struts and slab) is provided to be made up of HA Ø14 for the bearing rods and riders, HA Ø12 for the distribution rods and stirrups. Their gaping should meet with the technical standards.
|
Name of project |
Amount of project |
Amount of bid bond |
Cost of tender file |
|
Rehabilitation of the WAWA Bridge along the NSEH – MEMFU road stretch in Nkum Municipality |
50,000,000 CFA F |
250 000 CFA F |
70,000 CFA F |
Participation is open under the same conditions to all Cameroonian companies and business concerned that have proven experience in the field of Public works, especially roads and bridges construction.
The works, subject of this invitation to tender, shall be financed by the 2026 Public Investments Budget. The budgeted amount of the work is fifty million (50 000 000) FCFA
The file may be consulted during working hours at the NKUM Council, Contract Award Service, as soon as this notice is published
The file may be obtained from the NKUM council at the Secretariat of the Mayor, as soon as this notice is published against the payment of the sum of seventy thousand (70 000) CFA francs, payable at the competent Public Treasury, representing the cost of purchasing the Tender File.
Each offer drafted in English or French in 07 (seven) copies including 01 (one) original and 06 (six) copies marked as such, should reach the NKUM council, Contract Award Service not later than 02/07/2026 at 10:00 noon local time and should carry the inscription:
OPEN NATIONAL INVITATION TO TENDER N°: 012/ONIT/NKUM COUNCIL/NCITB/PIB-MINHDU/2026 OF 05/06/2026 FOR THE REHABILITATION OF THE WAWA BRIDGE ALONG THE NSEH – MEMFU ROAD STRETCH IN NKUM MUNICIPALITY; BUI DIVISION, NORTHWEST REGION.
«To be opened only during the bid opening session »
The offers or the bids submitted after the stipulated dateline shall not be received.
Bidders have tweenty-one (21) days for the submission of their bids with effect of the date of publication of the tender notice
Each bidder must include in his administrative documents a bid bond of the sum of two hundered and fifty (250,000) FCFA issued by a first-rate bank approved by the Ministry in charge of Finance featuring in the annex of the tender file.
The provisional deposit shall be automatically released not later than 30 (thirty) days following the expiry of the validity of the bids for bidders who shall not be retained. In the case where the bidder is awarded the contract, the provisional deposit shall be released after the constitution of the final bond.
The bids not respecting the separation mode of the financial bid from the administrative and technical bids shall be rejected.
Any bid not in conformity with the prescription of this tender notice and tender file shall be declared inadmissible. Especially the absence of a bid bond of a first-rate bank approved by the Ministry of Finance and valid for a period of thirty (30) days shall be rejected.
Least they are rejected, only the originals or certified true copies by the issuing service or administrative authorities of the administrative documents are accepted. They must obligatorily not be older than three (03) months and must be valid during the bid opening session.
The bids shall be opened in a single phase. The opening of the administrative documents, the Technical and Financial offers will take place on the 02/07/2026 at 11:00 AM local time, in the conference hall of the NKUM Council, by its competent members. Only bidders may attend or be represented by duly mandated persons of their choice and having a good knowledge of their files.
The evaluation of the bids shall be done in three (03) steps:
Ø 1st step: Verification of the conformity of the administrative file;
Ø 2nd step: Evaluation of the technical file;
Ø 3rd step: Analysis of the financial file.
The criteria of evaluation are the following:
14.1-Eliminatory criteria
14.1.1- Administrative documents
· Any offer not in conformity with the prescriptions of this tender file shall be declared inadmissible. Especially the lack of the provisional guarantee;
· Absence of a document in the administrative file;
· Any company having a 2024 project, notified to commence in 2024 and which has not yet been received;
· False declaration or falsified documents.
· Incomplete or non compliant documents ;
· False declaration, forged or scanned documents;
· Non existence in the technical file of the rubric « organization, methodology and planning »
· Technical assessment mark lower than 90% of “Yes”.
14.1.3- Financial offer
· Incomplete financial offer;
· Non compliant documents;
· Omission of quantified unit price in the financial offer;
· Modification of the model of schedule unit prices attached;
· Absence of prices breakdown.
Essential criteria:
The technical offer of the bidder shall be assessed along the following lines:
|
S/N |
Designation |
MARKS |
|
01 |
Quality of Requested staff: Qualifications, experience of personnel affected to the project, CV, NIC and attestation of availability signed and dated. |
05 |
|
02 |
Reference of the enterprise: § Turnover in the past two years; § Experience in road/public works |
02 |
|
03 |
Technical equipment/material affected to the project: The company should justify the property of the equipment necessary to the execution of works. |
03 |
|
04 |
Acknowledgement of site visit: § Attestation of site visit duly signed by the competent authority; § Site visit report; § Relevant illustrative pictures of the site; |
03 |
|
05 |
Presence of the methodology of work execution |
05 |
|
06 |
Presence of the prefinancing capacity |
01 |
|
07 |
General Presentation of the offer: Document spirally bound, colour sheets separation, table of content, presentation of documents in the order given in this tender file, quality of document. |
01 |
The note of the technical offer will be gotten by addition of marks for every criterias and only the technical offers having gotten an equal or superior note to 90% of YES will be allow passing the step of the financial evaluation.
The jobbing order shall be awarded to the bidder whose bid is in conformity with the dispositions of the tender file and on the basis of the lowest bid and technical quality. (See article 99 of the public contracts code).
The bidders shall remain committed to their bids during a period of (ninety) 90 days from the dateline set for the submission of bids.
Complementary technical information may be obtained during working hours from Nkum Council at the office of the Council Development Officer (CDO).