Système intégré de gestion ouvert et multiplateformes des marchés publics
Publié le 25-11-2026 à 09:59
Support : support@armp.cm Plateforme : pridesoft@armp.cm
PROJET GOUVERNANCE LOCALE ET COMMUNAUTÉS RÉSILIENTES
PRESS RELEASE No. 00000052/C/MINDDEVEL/SG/PROLOG/UGP/SPM/2026 OF 23 N0V 2026 Publishing the results of General Call for Expressions of Interest No. 00054/AGMI/MINDDEVEL/PROLOG/UGP/SPM/CA-SPM/2026 of 21 July 2026 for the prequalification of enterprises for the restricted tenders under the second funding cycle for the investments of the South-West Regional Assembly.
Source de financement

The National Coordinator of the Local Governance and Resilient Communities Project (PROLOG) hereby informs the public, and in particular the enterprises that expressed interest for the South-West Region, of the results of General Call for Expressions of Interest (GCEI) No. 00054/AGMI/MINDDEVEL/PROLOG/UGP/SPM/CA-SPM/2026 of 21 July 2026. This GCEI sought to preselect enterprises interested in carrying out climate-resilient inter-municipal infrastructure in the Adamawa, East, Far North, North, North-West and South-West Regions for fiscal years 2026 and 2027.

For the South-West Region, the applications were reviewed by the Ad Hoc Evaluation Commission established by Decision No. 00000130/D/MINDDEVEL/PROLOG/SPM/ASPM of 19 August 2026. The Commission, chaired by the Representative of the President of the South-West Regional Assembly, met on 27, 28 and 31 August 2026 and examined 65 applications from 44 enterprises and joint ventures. It then revised its evaluation report in October 2026 to take into account the observations of the review note of the PROLOG National Coordination of 13 October 2026.

Applications were subject to a verification of the minimum eligibility conditions and to a technical evaluation out of 100 points, with an eliminatory threshold of 70 points.

The results below are those of the revised report, which includes the corrections made by the South-West Regional Coordination Unit. These corrections concern the re-scoring of all applications on the published scale, the harmonization of the eligibility decisions between sub-projects, the eligibility of enterprises subject to a blacklisting measure by the Public Contracts Regulatory Agency (ARMP), taking into account the lifting decisions produced, and the arithmetic verification of the technical scores.

Accordingly, the enterprises and joint ventures listed below are declared prequalified. Each is entered on one or more of the four (04) shortlists below, for a total of fifteen (15) entries. These shortlists concern the sub-projects financed for the South-West Regional Assembly under the second cycle of the RCSG window.

Sub-project No. 19 – Construction and equipping of a District Hospital at Konye (Meme Division) – 3 enterprises

No.

Company name

1

BOOGY SARL

2

CHARIOT COMPANY LTD

3

JV AFUHCAM ENGINEERING COMPANY LTD AND NAF GEOTEK LTD

Sub-project No. 20 – Government Technical High School of Ekondo Titi, phase 1 (Ndian Division) – 3 enterprises

No.

Company name

1

BOOGY SARL

2

ETS LA PAIX D'AFRIQUE

3

REAL ESTATE CONSTRUCTION COMPANY LTD AND BUNDES CONSTRUCTION AND REAL ESTATE CO LTD

 

Sub-project No. 23 – 12 m permanent bridge over the Bego at Fotabong III (Menji council area) – 5 enterprises

No.

Company name

1

FOTABONG ROYAL ENTERPRISE CAMEROON

2

CAMEROON CONTRACTORS

3

ETS BOGHA AND SONS LTD

4

BUSINESS LINK CAMEROON

5

FOUNTAIN CONSTRUCTION COMPANY LTD (FOCOCOM)

 

Sub-project No. 24 – Three minor bridges linking Ngoh and Abeubeuh via Njentse (Menji, Lebialem Division) – 4 enterprises

No.

Company name

1

BUSINESS LINK CAMEROON

2

FOTABONG ROYAL ENTERPRISE CAMEROON

3

JV CAMEROON CONTRACTORS AND CLEAN-CUT CONSTRUCTION COMPANY (3C LTD)

4

CHARIOT COMPANY LTD

 

The South-West Regional Assembly, as Contracting Authority, will launch the restricted tenders. Prequalified enterprises will be invited to submit technical and financial bids only for the sub-project(s) for which they are shortlisted. Prequalification does not constitute the award of a contract, nor any commitment by PROLOG or the South-West Regional Assembly.

Contract award cap: at the end of the restricted tenders, no single enterprise may be awarded more than two (02) contracts out of the four (04) sub-projects covered by this press release. This cap also applies to contracts won as a member of a joint venture. The tender documents will set out how this rule is applied, in particular where a bidder ranks first on more than two sub-projects.

In accordance with the GCEI and the evaluation report, remaining on the shortlists is subject to the following conditions:

–    the results of the visit to the enterprises' offices, sites and facilities, which verifies their actual human and material capacities;

–    the authenticity of the documents submitted;

–    the lifting, before the invitation to bid, of the reservations set out in the evaluation report, which will be notified individually to the enterprises concerned.

Any false declaration or forged document will lead to the exclusion of the enterprise concerned, at whatever stage of the procedure it is detected. The sanctions provided for by the regulations in force and by the World Bank Guidelines will then apply.

Unsuccessful applicants may obtain the reasons for the rejection of their application. To do so, they must send a written request to the PROLOG South-West Regional Coordination Unit in Buea within [ 3] working days of the publication of this press release.

This press release will be published wherever necessary and posted at the headquarters of the South-West Regional Assembly and at the PROLOG South-West Regional Coordination Unit.

YAOUNDE Le 23-11-2026
Le COORDONNATEUR NATIONAL
NGWA EDIELLE THIERRY HERVE JACKSON